Manager: | Lars Söderström |
Start: | January 25, 2009 |
Finish: | June 1, 2009 |
Report Date: | March 16, 2009 |
WBS | Name | Start | Finish | Work | Priority | Complete | Cost |
---|---|---|---|---|---|---|---|
1 | Phase 1 | Jan 26 | Mar 12 | 33d 1h | |||
1.1 | Choose subject | Jan 26 | Jan 27 | 2d | 100% | ||
1.2 | Choose supervisor | Jan 28 | Jan 28 | 1h | 100% | ||
1.3 | Do a quick litterature study | Jan 28 | Feb 11 | 10d | 100% | ||
1.4 | Make a project plan | Feb 11 | Feb 13 | 2d | 100% | ||
1.5 | Write chapter 1 first draft | Feb 13 | Feb 20 | 5d | 100% | ||
1.6 | Get feedback on chapter 1 | Feb 20 | Feb 20 | ||||
1.7 | Rewrite chapter 1 with feedback | Feb 20 | Feb 24 | 2d | 100% | ||
1.8 | Write Questionnaire | Feb 24 | Feb 26 | 2d | 100% | ||
1.9 | Configure svn account and add all relevant files to versioning system | Feb 26 | Mar 2 | 2d | 100% | ||
1.10 | Test method and rewrite if needed | Mar 2 | Mar 9 | 5d | 100% | ||
1.11 | Get feedback on Rewritten chapter 1 and questionnaire | Mar 9 | Mar 9 | ||||
1.12 | Fix the last issues on chapter 1 and questionnaire | Mar 9 | Mar 12 | 3d | 0% | ||
1.13 | Phase 1 finished | Mar 12 | Mar 12 | ||||
2 | Phase 2 | Mar 12 | Apr 20 | 27d | |||
2.1 | Write background chapter first draft | Mar 12 | Mar 23 | 7d | 0% | ||
2.2 | Get feedback on background chapter | Mar 23 | Mar 23 | ||||
2.3 | Rewrite background chapter according to feedback | Mar 23 | Mar 24 | 1d | 0% | ||
2.4 | Implement problem 1 in Java | Mar 24 | Mar 26 | 2d | 0% | ||
2.5 | Implement problem 1 in Ruby | Mar 26 | Mar 30 | 2d | 0% | ||
2.6 | Answer Questionnaire | Mar 30 | Mar 30 | 2h | 0% | ||
2.7 | Draw conclusions from problem 1 | Mar 30 | Mar 30 | 2h | 0% | ||
2.8 | Get feedback on the first experiment | Mar 30 | Mar 30 | ||||
2.9 | Refine the method and apply relevant feedback if needed | Mar 30 | Mar 31 | 1d | 0% | ||
2.10 | Implement problem 2 in Ruby | Mar 31 | Apr 2 | 2d | 0% | ||
2.11 | Implement problem 2 in Java | Apr 2 | Apr 6 | 2d | 0% | ||
2.12 | Answer Questionnaire | Apr 6 | Apr 6 | 2h | 0% | ||
2.13 | Draw conclusions from problem 2 | Apr 6 | Apr 7 | 2h | 0% | ||
2.14 | Write the data chapter and relevant appendixes | Apr 7 | Apr 16 | 7d | 0% | ||
2.15 | Get feedback on the first ieration of phase 2 | Apr 16 | Apr 16 | ||||
2.16 | Update the background and data chapter where needed | Apr 16 | Apr 20 | 2d | 0% | ||
2.17 | Phase 2 finished | Apr 20 | Apr 20 | ||||
3 | Phase 3 | Apr 20 | May 14 | 18d | |||
3.1 | Write the conclusions and lessions learned | Apr 20 | Apr 27 | 5d | 0% | ||
3.2 | Get feedback on conclusions and lessons learned | Apr 27 | Apr 27 | ||||
3.3 | Rewrite conclusions and implement feedback | Apr 27 | Apr 28 | 1d | 0% | ||
3.4 | Write the summary | Apr 28 | Apr 30 | 2d | 0% | ||
3.5 | Write the abstract | Apr 30 | May 1 | 1d | 0% | ||
3.6 | Get feedback on summary and abstract | May 1 | May 1 | ||||
3.7 | Rewrite summary and abstract as needed | May 1 | May 4 | 1d | 0% | ||
3.8 | Spell check complete text | May 4 | May 6 | 2d | 0% | ||
3.9 | Do a final rewrite of sections that needs it | May 6 | May 12 | 4d | 0% | ||
3.10 | Get feedback of almost done thesis | May 12 | May 12 | ||||
3.11 | Rewrite parts of thesis if needed | May 12 | May 14 | 2d | 0% | ||
3.12 | Phase 3 Finished | May 14 | May 14 | ||||
4 | Phase 4 | May 14 | May 22 | 6d 5h | |||
4.1 | Make a presentation for the seminar | May 14 | May 15 | 1d | 0% | ||
4.2 | Present my findings | May 15 | May 15 | 2h | 0% | ||
4.3 | Defend my findings | May 15 | May 15 | 2h | 0% | ||
4.4 | Take relevant notes of good points from the oposition | May 15 | May 15 | 1h | 0% | ||
4.5 | Implement changes in thesis | May 15 | May 22 | 5d | 0% | ||
5 | Phase 5 | May 22 | Jun 1 | 6d | |||
5.1 | Read opponents thesis | May 22 | May 27 | 3d | 0% | ||
5.2 | Write an opposition report | May 27 | May 29 | 2d | 0% | ||
5.3 | participate actively on opponents presentation | May 29 | Jun 1 | 1d | 0% |
Name | Short name | Type | Group | Cost | |
---|---|---|---|---|---|
Beatrice Åkerblom | Beatrice | Work | Tutor | 0 | |
Lars Söderström | Lars | Work | Student | 0 |